Airport Blvd Bridge Deck Replacement - Mobile, AL

Project: Airport Blvd Bridge Deck Replacement

Prime Contractor: McElhenney Construction

Owner: Alabama Department of Transportation

Scope of Work: 

The Alabama Department of Transportation(ALDOT) bid an emergency partial bridge deck replacement for a 22' x 7' section of the bridge to be replaced .

For 43 straight hours, MCC team members worked diligently to remove, form, and pour the designed area. After receiving the required cylinder break, the temporary traffic control was removed and the bridge opened to traffic. 

The contract time to remove, replace, and open to traffic was 10 working days. MCC finished eight days ahead of schedule. 